All underground services are complete. All staircases are installed. Bathroom waterproofing is complete, and tiling is in progress. Internal fixing is underway….
Ashton Park, July 2018
We are pleased to provide you with the progress achieved on site so far.
Block work for building A complete. Starting building B block work.
We will be forming suspended concrete slab for the first floor in the next few weeks.