Ashton Park, Jan 2019
We are pleased to update you on the construction status for 338-340 Burwood Highway, Burwood.
Building B Framing will be completed within 2 weeks, all windows have been installed.
Building A Framing will be completed within 3 weeks. windows installation is underway
Anticipated settlement period: April / May 2019.
We will keep you posted as we progress through the next phase.