Bored piers are complete. Capping beams have been successfully installed. Retaining walls are now finished. Inground plumbing works are well underway. Bulk…
Ashton Park, Apr 2019
We are pleased to update you on the construction status for 338-340 Burwood Highway, Burwood.
– Building B scaffold has been removed.
– Kitchen, cabinets are currently under installation.
– Stairs have been installed, except for ground floor stairs.
– Building A scaffold will be removed this week.
– Once all the scaffold is removed, the driveway and landscape to follow.
We are currently anticipating June settlement period.
We have engaged settlement solution as our settlement agent. Should you have any question, regarding settlement matter, please do not hesitate to contact with the below details: