Wall framing complete Roof trusses in progress Plumbing stack work underway Please see below the photos taken from the site:
Altus, September 2019
We are pleased to provide you with the progress achieved on-site so far.
We are pleased to provide you with the progress achieved on-site so far.
– Currently, the building is at the lock-up stage
– Windows have been installed on the ground and first floor.
– Ground floor plaster has been completed, first-floor plaster is half wat through.
Currently anticipated construction completion before Christmas 2019.
In preparation for settlement, we advise all purchaser to start speaking to their bank & broker to organize settlement finance to suit this timeline.
We will keep you posted as we progress through the next phase.