Bored piers are complete. Capping beams have been successfully installed. Retaining walls are now finished. Inground plumbing works are well underway. Bulk…
Altus, November 2019
We are pleased to provide you with the progress achieved on-site so far.
Construction:
– Kitchen Joinery has been installed up to 50%
– Plaster works have been completed up to 100%
– Paintworks has been completed up to 50%
– Services works have been completed up to 80%
– The landscape will be expected to finish by next week.
The titles are expected to be registered prior to Christmas 2019
We will be ready for valuer inspection:
– Ground Floor/First Floor: First week of December 2019
– Second/Third/Fourth Floor: Second Week of December 2019
We will be ready for purchaser inspection:
– Ground Floor/First Floor: Second week of Jan 2020
– Second/Third/Fourth Floor: Third week of Jan 2020
We are currently aiming for an early February 2020 settlement at this stage.