Entire ground floor concrete slab pour – Complete Ground floor wall framing for Units 6-8 – Complete Ground floor wall framing for…
Altus, June 2019
We are pleased to provide you with the progress achieved on site so far.
Ground floor framing completed, rough-in will start soon.
Level 1: Framing nearly completed, currently doing internal rough-in
Level 2: Currently doing framing
Level 3: Framing will start soon.
Level 4: Currently doing the framing, the roof will be expected on early-mid July.
Currently anticipated construction completion will be late November- early December 2019. We will keep you posted as we progress through the next phase.gh the next phase.

