All underground services are complete. All staircases are installed. Bathroom waterproofing is complete, and tiling is in progress. Internal fixing is underway….
Altus, June 2019
We are pleased to provide you with the progress achieved on site so far.
Ground floor framing completed, rough-in will start soon.
Level 1: Framing nearly completed, currently doing internal rough-in
Level 2: Currently doing framing
Level 3: Framing will start soon.
Level 4: Currently doing the framing, the roof will be expected on early-mid July.
Currently anticipated construction completion will be late November- early December 2019. We will keep you posted as we progress through the next phase.gh the next phase.