All underground services are complete. All staircases are installed. Bathroom waterproofing is complete, and tiling is in progress. Internal fixing is underway….
Altus, August 2019
We are pleased to provide you with the progress achieved on-site so far.
Ground floor: Services rough-in and internal sheeting is 80% completed. Windows frames have commenced installing now.
Level 1: Rough-in and internal sheeting is 60% complete.
Level 2: Rough-in and internal sheeting is 50% complete.
Level 3: Rough-in and internal sheeting is 30% complete.
Level 4: Roofing complete, rough-in started.
Currently anticipated construction completion will be late November- early December 2019.
In preparation for settlement, we advise all purchaser to start speaking to their bank & broker to organise settlement finance to suit this timeline.
We will keep you posted as we progress through the next phase.