1975, May 2021

  |  Construction Updates

We are pleased to provide the progress achieved on-site to date for 1975 Malvern East.

The following is the progress of the works to date:

  • Roofing installation: 100% Completed
  • Windows installation: 100% Completed
  • Services rough in: 90% Completed
  • External cladding: 80%
  • Stair installation to commence early June
  • Internal plastering to commence in 1.5 weeks

Project completion currently is still forecasted to be achieved by October 2021. Settlement is anticipated to be sometime in November 2021.

Please note as always timings are always anticipated and an exact settlement date will not be known until the Plan of Subdivision has been registered with the Titles Office and the Certificate of Occupancy achieved, and settlement is called.

It is recommended to commence the finance process if you require one. Please do not underestimate the amount of time required to complete the finance process to ensure you are organized for a smooth and timely settlement.