We are pleased to provide the progress achieved on-site to date for 1975 Malvern East.

The following is the progress of the works to date:

  • Heating and cooling units installation – 100% completed
  • Internal wall painting – 60% completed
  • Waterproofing to wet areas – 80% completed
  • Floor tiling – 20% completed
  • Fixtures and fittings – 50% completed
  • Landscaping works have commenced

We anticipate project completion to be achieved by October/November 2021. Settlement is still anticipated to be around November or December 2021.

Please note as always timings are always anticipated and an exact settlement date will not be known until the Plan of Subdivision has been registered with the Titles Office and the Certificate of Occupancy achieved, and settlement is called. However, please rest assured that we are doing everything we can to deliver the project to you as soon as we can.

It is highly recommended to commence the finance process if you require one. Please do not underestimate the amount of time required to complete the finance process to ensure you are organized for a smooth and timely settlement.